Re-Insulating an Aging Storage Tank Without Shutting the Plant Down

Release Time:

2026-10-08


The hardest part of fixing a corroding storage tank is rarely the coating. It is the shutdown. Taking a tank out of service to strip cladding, blast the shell and re-lag it can cost more in lost throughput than the repair itself — which is why so many tanks are left to quietly rust under their insulation. A bonded aerogel coating changes that maths, because the work can be done on a live, in-service shell.

Here is the sequence ENZE CHEMICAL uses on retrofit projects of this kind.

1. Assess without stripping. Because the coating bonds to the prepared steel rather than wrapping it, you do not need to remove the entire existing lagging up front. Inspect exposed and sampled areas, confirm substrate soundness, and scope only the zones that need attention.

2. Prepare the steel to spec. As with any protective system, surface preparation sets the outcome. Remove loose rust, salts and failed coating to the specified standard. The shell stays in service throughout — no gas-freeing of the whole vessel, no full isolation.

3. Prime where the system calls for it. Single-component waterborne aerogel coatings are supplied ready to use, but some duties need a primer layer for adhesion on older steel. Apply it locally; there is no oven bake, cure is ambient.

4. Apply to design thickness. Spray, roller or trowel the coating as one monolithic layer. Total dry film is only 0.3–6 mm, so coverage of nozzles, manways and stiffeners is straightforward and there are no bands or cladding to fit. Touch-dry in around four hours means a shift can prime and coat the same zone.

5. Verify and move on. Any impact damage shows on the outside of the coating and is repaired in place. Thermal conductivity is 0.030–0.046 W/(m·K), hydrophobic grades hold a water contact angle of 110° or more, and because there is no annular cavity, the CUI mechanism that drove the original failure is removed rather than hidden.

The reason this works on a live tank is structural, not cosmetic. A wrapped mineral-wool system needs the vessel isolated so crews can strip and re-clad safely; a bonded coating is applied like any maintenance paint, in zones, while the tank keeps operating. Standard grades cover −40 °C to 150 °C and are rated seven years or more outdoors, so the retrofit is a genuine repair, not a stopgap.

For operators sitting on a fleet of aging tanks, that reframes the backlog. The question stops being "which tank can we afford to take down this year" and becomes "which zones do we coat next shift" — and the corrosion under the old insulation finally gets dealt with instead of deferred.

Back to previous page

Get A Free Quote


I Want More Details. Product Requirement: Custom Made: Delivery Time: Payment: Shipping: Usage:
((Luta 5 arquivos. Suporta jpg, jpeg, png, gif, txt, doc, pdf, xls, doc, xlsx, leitura de 5MB))
SUBMIT